Figure 5. No Side Push Label
IMPORTANT: The rack may only be moved up or down a maximum incline/decline of 5 degrees.
3. Position the rack to its final location and lower the leveling feet using a 13mm wrench.
4. Use a bubble level to verify the rack is level.
5. From the bottom up, repeat the steps above to insert the disk drives into the remaining enclosures. See
Install
Disk Drives in a 5U84 Enclosure
on page 19 and
Install Disk Drives in a 2U24 Enclosure
on page 25.
Move the Rack to its Final Position
18
Содержание ClusterStor L300
Страница 1: ...ClusterStor L300 and L300N Field Installation Guide 3 0 0 H 6163...
Страница 33: ...Figure 18 Trip the Circuit Breaker Cable the External Power Connections 33...
Страница 90: ...MGMT0 cscli unmount f testfs Perform the First Run Configuration 90...
Страница 125: ...Figure 85 Base Rack Inverted Power Distribution for PX2 5965X3 V2 ClusterStor L300 and L300N Reference 125...