![Cisco CRS-16-LCC/M Скачать руководство пользователя страница 112](http://html.mh-extra.com/html/cisco/crs-16-lcc-m/crs-16-lcc-m_installation-manual_63756112.webp)
The figure shows the front (PLIM) side of the LCC with a modular configuration power system installed.
Figure 50: LCC Front (PLIM) Side Slot Numbers
Power Up a Chassis with Modular Configuration Power
This section describes how to power up a chassis with modular configuration AC or DC power shelves installed.
Prerequisites
Before performing this task, you must install and wire the power shelves, install the PMs and alarm modules,
and install the route processor (RP) card. See
Installing a Modular Configuration Power Shelf
,
Modular Configuration Power Module
Installing a Modular Configuration Alarm Module
, and
. If you have a modular configuration DC power system installed, wiring at the BDFB
or at the power plant should be complete.
Steps
To power on the chassis, perform the following steps:
Cisco CRS Routers 16-Slot Line Card Chassis Installation Guide
92
Installing and Removing Power Components
Power Up a Chassis with Modular Configuration Power
Содержание CRS-16-LCC/M
Страница 20: ...Cisco CRS Routers 16 Slot Line Card Chassis Installation Guide xx Preface Preface ...
Страница 118: ...Cisco CRS Routers 16 Slot Line Card Chassis Installation Guide 98 Installing and Removing Power Components Steps ...
Страница 252: ...Cisco CRS Routers 16 Slot Line Card Chassis Installation Guide 232 Upgrading Chassis Components Steps ...