49
CLASSIC EDGE OUTDOOR FURNACE • OWNER'S MANUAL
10. Install the disc onto the air tube making sure the disc fits evenly. Install
the cotter pin through the solenoid and disc; then bend the ends of the
pin to prevent it from falling out.
11. Connect the wires disconnected in step 3.
12. Manually lift the solenoid and let it fall several times to ensure nothing
can obstruct its operation. Perform the same check on all other solenoids
in this compartment.
13. Close and secure the airbox cover. Install the outer airbox cover and
secure with screws; then connect power to the furnace and test solenoid
operation.
Do not connect power or operate the outdoor furnace with the outer airbox cover
removed. The outer airbox cover must be installed and secured with screws.
NOTE: The factory settings for air regulating discs are shown below.
MODEL
3/8"
(9.5 mm)
5/16"
(8 mm)
3/8"
(9.5 mm)
5/16"
(8 mm)
350
1/4" (6 mm)
5/8" (16 mm)
550
1/4" (6 mm)
13/16" (21 mm)
750
SECONDARY AIR
SECONDARY
STAGE 3
Stage 3
Solenoid
Stage 3
Solenoid
Stage 1
Solenoid
STAGE 2
STAGE 1
PRIMARY AIR
PRIMARY
SECONDARY AIR CHARGE TUBE AND REFRACTORY MODULES
Remove all wood, coals and ash from the firebox and allow the firebox to cool
thoroughly before replacing the secondary air charge tube and/or refractory.
Secondary Air Charge Tube and
Refractory Removal Procedure