INSTRUCTIONAL MANUAL
2750L-P/4500L-P/6000L-P
August, 2001
Rev. K
-88-
4.3 PERIODIC
CALIBRATION
The following periodic calibration adjustments should be performed on a 1 year interval.
4.3.1 VOLTAGE
CALIBRATION
Apply power top the AC Power System and allow at least fifteen minutes for temperature stabilization. Program the
output to 60 Hz, 135 volts and perform the following steps:
1.
Connect the AC voltmeter to the phase to be calibrated.
2.
Depress the MNU key several times until the first menu screen is displayed as illustrated below.
SNC = 01
*CLK = 02
*WVF = 03
RNG = 04
*May not be displayed. Depends on configuration.
3.
Enter the key sequence: 959 ENT
4.
Depress the MNU key several times until the configuration menu screen is displayed as illustrated
below:
CFG
=
16
ALM
=
17
FLM = 18
CLM = 19
5.
Select the CAL screen with the key sequence: 12 ENT
6.
Depress the A, B or C key for the output phase to be calibrated. Verify that the other phases are in the
MON mode. The A, B, or C keys will switch the respective phase between the MON and PRG mode.l
If the output voltage is greater than the programmed output, depress and hold the
↓
key until the
correct output voltage has been reached. The
↑
key is used if the output is less than the programmed
value.
7.
Repeat step 6 for other outputs to be calibrated.
4.3.2 VOLTAGE
MEASUREMENT CALIBRATION
For calibration of voltage measurement first perform the output voltage calibration and then perform the followings
steps:
1.
Remove the load from the AC Power System and program 60 Hz and 135.0 volts.
2.
Depress the MNU key several times until the Menu screen is displayed as illustrated below:
SNC = 01
*CLK = 02
*WVF = 03
RNG = 04
*May not be displayed. Depends on configuration.
3.
Enter the key sequence: 959 ENT.
Содержание 12000L-1P
Страница 27: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 23 Figure 2 3 FUNCTION TEST SETUP...
Страница 98: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 94 Figure 4 3 FLOW DIAGRAM A REMOTE CALIBRATION...
Страница 99: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 95 Figure 4 3 FLOW CHART continued...
Страница 108: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 104 This page left intentionally blank...
Страница 110: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 106 Figure 5 1 AC POWER SYSTEM BLOCK DIAGRAM...
Страница 114: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 110 This page left intentionally blank...
Страница 119: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 115 Figure 6 1 MODULE LOCATION...
Страница 120: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 116 This page left intentionally blank...
Страница 133: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 129 Figure 1 STEADY STATE VOLTAGE...
Страница 135: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 131 Figure 8 9 FREQUENCY TRANSIENT...
Страница 136: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 132 Figure 10 11 ABNORMAL OPERATION...
Страница 137: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 133 Figure 12 13 ABNORMAL FREQUENCY...
Страница 138: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 134 Figure 14 EMERGENCY VOLTAGE...
Страница 140: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 136 This page left intentionally blank...
Страница 148: ...INSTRUCTIONAL MANUAL 2750L P 4500L P 6000L P August 2001 Rev K 144 FIGURE 2...