InstALLAtIon
BASIC INSTALLATION REQUIREMENTS
The equipment is to be connected from/to the return header pipework of the appropriate
sealed system. The maximum pipe run length from the system pipework to the BOSS™
X-POT6+ is to be 10m.The 2 connections, from/to the return pipework, for the BOSS™
X-POT6+ is to be made at the bottom / underside of the return pipework to allow for any
dense particulate solids to be drawn into the BOSS™ X-POT6+ for active removal from the
system. A 1” drain with isolation valve is supplied at the bottom of the vessel. Extend this
drain to a local floor gully with a minimum fall of 1:100.
The Power supply to the BOSS™ X-POT6+ is to be provided from the main system pump
electrical supply. Therefore, the BOSS™ X-POT6+ will only be activated when the main
system pump is running and active.
Ensure the power supply is 230V ~ 1 N PE 50Hz via a
suitable Fused Spur.
CRITICAL INSTALLATION REQUIREMENTS
The equipment must be sited:
• In a frost free area (> 5°C) and must also be protected from adverse environmental
conditions
• In a well-lit area to allow for safe changing of the filter media and chemical dosing
• On a flat, vertical, level, solid wall with clear access to the electrical panel, pump and
BOSS™ X-POT6+ vessel itself
Care must be taken when handling this equipment. Appropriate safety measures must
be
in place in respect of use, handling and application of:
• Electrical equipment
• Hydraulic equipment
• Pressure vessels
• Manual handling
• Sealed system water
• Chemical inhibitors and additives
• Powerful Rare Earth magnets
• Particulate debris
• Filter media
It is essential to ensure the environment that this equipment is installed in is safe to work