Operation
Instruction handbook
b maXX
5800
Document No. 5.16027.04
119
8
Commissioning
.
The following preconditions must be fulfilled before commissioning:
1 b maXX 5800
with VARAN is installed correctly.
n
Ethernet connection cables are wired correctly.
2
The control cabinet is properly locked and all safety devices are operating.
3
The
b maXX 5800
device is ready-to-use.
4
Create a Lasal-Class2 project using the driver classes for
b maXX 5800
drives for cy-
clic and service data communication.
5
Start the VARAN control
Parameters
The parameter settings determine the behavior of the VARAN slave in operation. Param-
eters are set with the software ProDrive.
1
Start ProDrive
2
Click on „Project Tree“.
3
Communication settings with ProDrive
n
Project Tree: Configuration/Fieldbus slave
(refer also Parameter manual
b maXX 5800
)
m
Set Synchronization to „On“
m
Set Fieldbus cycle time according VARAN cycle time (1 ms, 2 ms, 4 ms or 8 ms)
m
Set Source sync signal to fieldbus
Содержание b maXX 5000 BM5800 Series
Страница 158: ...Recommissioning Instruction handbook b maXX 5800 Document No 5 16027 04 Baumüller Nürnberg GmbH 158 of 174 12 6 ...
Страница 164: ...Instruction handbook b maXX 5800 Document No 5 16027 04 Baumüller Nürnberg GmbH 164 of 174 ...
Страница 165: ...165 of 174 Operation Manual b maXX 5800 Document no 5 16027 04 APPENDIX B DECLARATION OF CONFORMITY ...
Страница 168: ...Operation Manual b maXX 5800 Document no 5 16027 04 Baumüller Nürnberg GmbH 168 of 174 ...
Страница 174: ...Instruction handbook b maXX 5800 Document No 5 16027 04 Baumüller Nürnberg GmbH 174 of 174 Notes ...
Страница 175: ......