Step 17
Attach a
M7 Wall Cap
to G2 and G3 with a ½” overhang and 3 3/8” from outside of G8 and G5 using 3” Wood
Screws.
Attach
M1 Roof Cap
and
M2 Ridge Cap
to
F1 Roof Rafters
with 1 ½” Wood Screws now repeat and attach Rafter
assemblies together using 5/16” x 1” Bolts, Lock Washers, 5/16” x 5/8” Barrel Nuts and Lock Washers.
Set Roof Assembly on top of set and attach to Tower Legs with 2” Wood Screws.
Starting at peak of roof attach a
R1 Roof Slat
flush at peak and with a 1 ½” overhang at front and back and secure to
rafters using 1 ½” Wood Screws. Flush another R1 to the one just installed and then five more to each side. Finish
Roof by attaching a
R2 Inner Roof Slat
to each side using 1 ½” Wood Screws.
Attach a
A100011 Triangle Plates
to F1 Rafters at gable on front and back of set using three #14 x 1” Truss
Screws
.
M7
M7
F1
F1
F1
M1
M2
1 ½”
Overhang
R1
R1
R2
ITEMS NEEDED
2-M7 Wall Caps
2-M1 Roof Caps
2-M2 Ridge Cap
12-R1 Roof Slats
2-R2 Inner Roof Slats
6-F1 Rafters
HARDWARE NEEDED
6-3” Wood Screws
80-1 ½” Wood Screws
2-5/16” x 1” Bolts
2-5/16” x 5/8” Barrel Nuts
2-5/16” Lock Washers for Bolts
1/2”
Over Hang
1/2”
Over Hang
PAGE 39
2-5/16” Lock Washers for Barrel Nuts
8-#14 x 1” Truss Screws
2-A100011 Triangle Brackets
4-2” Wood Screws
G8
G2
G3
G5
3-3/8”
3-3/8”
R1