MASTER
–
Instruction
Manual
Chap. 4
-
28
/32 -
ANCHORING THE TGV TABLES
3 of 3
STEP
ACTION
DESCRIPTION
4
Check
levelling
Check that the machine is level along the Y axis by placing the
precision level halfway along the length of the Y axis re-circulating
ball bearing screw, or halfway along the length of one of the Y axis
linear guides.
5
Level
Act on the four adjustment screws (
2
) located at the extremities of the
table. Tighten or loosen the screws by 1/4 turn at a time.
6
Check
levelling
Check levelling along the Y axis to make sure that the table is perfectly
levelled along Y.
7
Check
levelling
Check levelling along the X axis by resting the precision level along
the shelf’s linear guides.
8
Level
Act on the four adjustment screws (
2
) located at the extremities of the
table. Always tighten or loosen one pair of opposite screws by 1/4 turn
at a time.
9
Anchor the
screws
Check levelling along the X axis to make sure that the table is
perfectly levelled along YX
10
Apply the
dowels
Measure the verticality between the X and Y axes. Anchor the base of
the comparator to the body of the electro-spindle. Rest the point of the
comparator against the table resting bars. Shift the Y axis to the two
extremities of its stroke and verify the verticality of the axes.
Содержание MASTER
Страница 4: ...Chap 0 IV 4 Page intentionally left blank ...
Страница 5: ...CHAPTER 1 Foreward Chap 1 1 16 1 Foreword CHAPTER ...
Страница 7: ...CHAPTER 1 Foreward Chap 1 3 16 Page intentionally left blank ...
Страница 20: ...MASTER Instruction Manual Chap 1 16 16 Page intentionally left blank ...
Страница 21: ...CHAPTER 2 Safety information Chap 2 1 36 2 Safety information CHAPTER ...
Страница 56: ...MASTER Instruction Manual Chap 2 36 36 Page left intentionally blank ...
Страница 57: ...Chap 3 1 27 CHAPTER 3 Machine description and technical data 3 Machine description and technical data CHAPTER ...
Страница 59: ...Chap 3 3 27 CHAPTER 3 Page intentionally left blank ...
Страница 83: ...Chap 3 27 27 CHAPTER 3 ...
Страница 84: ...CHAPTER 4 Installation Chap 4 1 32 4 Installation CHAPTER ...
Страница 110: ...CHAPTER 4 Installation Chap 4 27 32 ANCHORING THE TGV TABLES 2 of 3 STEP ACTION DESCRIPTION 3 Positioning diagram ...
Страница 116: ...CHAPTER 5 Controls and Use of the machine Chap 5 1 62 5 Controls and use of the machine CHAPTER ...
Страница 178: ...CHAPTER 6 Maintenance Chap 6 1 30 6 Maintenance CHAPTER ...
Страница 207: ...MASTER Instruction Manual Chap 6 30 30 Page left intentionally blank ...
Страница 208: ...CHAPTER 7 Messages Alarms Chap 7 1 31 7 Messages Alarms CHAPTER ...
Страница 238: ...CHAPTER 7 Messages Alarms Chap 7 31 31 Page left intentionally blank ...