3-1
3 Open-box Inspection
Summary
Describing the inspection procedures.
Describing the open-box procedures.
3.1 Checking Packing List and Goods
Caution
Because ZXCBTS equipment is expensive, ensure that it is packed well and the
flags for avoiding water and vibrations are marked. Load and unload the
equipment gently, and avoided damage from sunshine and rain.
1. Check the “ZTE delivery sheet”.
2. Open-box inspection should be done by the engineering supervisor and your
representative. First, check if the total quantity of the goods is correct according
to the packing list, if the packing boxes are in good condition, and if the delivery
location is the right installation site.
3. Next, open the boxes and the engineering supervisor should check the goods
based on the packing list.
Open-box Inspection Report
is put in the packing box
numbered 1#. Open the 1# box and take out the
Open-box Inspection Report
to
check if the total quantity of the goods is consistent with the checklist, and then
archive the report.
4. During the inspection, if loss of goods, lack of goods, error delivery or any
damage is found, find out the cause and feedback to the ZTE headquarter for
handling.
5. The goods are packed in either cartons or wooden boxes. You need to open them
on site using different tools.