ZXCBTS (V5.4) CDMA Micro Base Transceiver Station & Remote Station Installation Manual
10-8
10.3 Installation and Replacement of Modules
Note
The modules and cables in Micro-BTS/remote stations have been installed,
connected and tested before delivery. Before commissioning, you only need to
check if they are loose due to conveyance.
According to the configuration requirement, you might need to add optical
fiber modules or CSM5000 expansion modules in the expansion slots of the
corresponding BDM board.
If any fault occurs, the maintenance personnel can refer to this manual for
simple maintenance.
10.3.1 Installation Sequence
Note
This section describes the sequence of module installation and cable connection
in an M800 micro-BTS. Refer to this sequence for the installation in
M801T/M802T/M190T/M191T/M192T/R800T/R190T/R191T/R192T
micro-BTS.
1. Install MTRX, BDM and BRFS.
2. Install T1 lightning arrester and lay T1 cables.
3. Connect Terminal B of DCDX02 and RSTDX to MPA and BRFS respectively,
and bundle the cables with cable ties on the cable tie bases.
4. Install MPD, BGPS, MGPS, MDIV, MLNA, MPA, RF and GPS lightning
arrester.
5. Lay interconnection cables between modules, access control cable and door
grounding cable, and connect the antistatic wrist strap.
6. Connect Terminal B of the RF cable RF27 to MDUP_ANT loosely. Next, install
MDUP in the cabinet and then fasten it. Finally, connect the other two RF
connectors on MDUP.
7. Install the heater, power lightning arrester and connect the relative cables
(including ACDX01).
10.3.2 Table of Cable Connections
Refer to Appendix B.