The image shows the principles of a piping installation with all components.
Figure 18: Principle solution for a piping installation .
Figure 19: Principle solution for a brine installation .
2 .11
Installation principle, Geysir Air
Filling kit incl.
strainer
Safety valve, 1.5 bar
Location of the bleed and expan-
sion tank when the outdoor unit is
located at the same level or lower
than the heat pump.
NOTE! The fluid level in the tank
must be above the highest point
of the outdoor unit.
Filler cock incl.
strainer
Shut-off valve
Brine out
Brine in
Strainer
Location of expansion tank, pres-
sure gauge, and safety valve (1.5
bar) at pressurised brine circuit
when the outdoor unit is positio-
ned higher than the heat pump.
Safety valve,
Pressure gauge
Filler tap
HW = Hot water
CW = Cold water
Exp = Expansion
Exp BRINE = Expansion
brine circuit
HW
Expansion
tank
To
outlet
Supply pipe
Return pipe
Safety valve, 9 bar
cold water
CW Exp
Shut-off valve
and strainer
Exp BRINE
Flexible hoses