Initialisation of an IVC unit after replacement
International L – edition: 17.02.2006
71
20.5
Machine specification self-test
ATTENTION! At the end of the initialistion, the IVC unit has to run a self-test to identify the spiral mo-
tors. You can carry out this test in service program 07, button 7 (
Therefore:
Press key S until display shows
Press button 7 Motor test starts
All available selections are operated once. This test tries also to
run all selections which are not available such as disconnected
motors or trays and disables them if noted. The same applies af-
ter adding trays the relevant selections will be enabled. The cur-
rent tested compartment is shown in the last two characters.
Press key C.
Finally leave the service program (
07 TEST PROGRAM
SELECTION:
07 =7 10
SELECTION:
07 =7 89