![Wood-mizer LT40 AH Series Safety, Setup, Operation & Maintenance Manual Download Page 34](http://html1.mh-extra.com/html/wood-mizer/lt40-ah-series/lt40-ah-series_safety-setup-operation-and-maintenance-manual_994651034.webp)
Setup & Operation
Sawmill Setup
2
2-1
HDSdoc030722
Setup & Operation
SECTION 2 SETUP & OPERATION
2.1
Sawmill Setup
IMPORTANT!
Before starting to use the sawmill you have to meet the
following conditions:
Set up the sawmill on firm, level ground and level the sawmill. Secure the sawmill to the
ground to prevent moving during operation. A concrete foundation or pads (rated to support
31 T/m
2
at each sawmill foot position) and 16mm anchored bolts are recommended.
Under roof, the sawmill should always be operated with the sawdust collection system.
The sawmill can’t be operated outdoor when it is raining/snowing and in case of rain/snow
the sawmill must be stored under roof or indoor.
The sawmill can be operated in temperature range from -15
o
C to 40
o
C only.
Illumination at operator's position must be 300lx.