72 Mounting
WAGO-I/O-SYSTEM 750 XTR
750-352/040-000 FC ETHERNET G3 XTR
Manual
Version 1.3.0
5.6.2
Removing the Fieldbus Coupler/Controller
1.
Use a screwdriver blade to turn the locking disc until the nose of the locking
disc no longer engages behind the carrier rail.
2.
Remove the fieldbus coupler/controller from the assembly by pulling the
release tab.
Electrical connections for data or power contacts to adjacent I/O modules are
disconnected when removing the fieldbus coupler/controller.
Pos: 51.19 /Serie 750 ( WAGO-I/O-SYST EM)/Monti eren/D emonti eren/XTR-I/O-Modul ei nfüg en @ 28\mod_1486551092321_21.docx @ 405487 @ 3 @ 1
5.6.3
Inserting the I/O Module
1.
Position the I/O module so that the tongue and groove joints to the fieldbus
coupler/controller or to the previous or possibly subsequent I/O module are
engaged.
Figure 33: Insert I/O Module (Example)