Mechanical Installation
Mechanical Mounting
FC 300 IP20 Frame sizes A1, A2 and A3 allow side-by-side installation. Due to cooling conditions, there
must be a minimum of 4 in. [100 mm] free air passage above and below the FC 300.
If the IP 21 Enclosure kit (130B1122 or 130B1123) is used, there must be a min. clearance of 2 in. [50
mm] between the drives.
B1, B2, C1 and C2 enclosures allow for side-by-side installation.
1.
Drill holes in accordance with the measurements given.
2.
You must use screws that are suitable for the surface on which you want to mount the FC 300.
Retighten all four screws.
Mounting frame sizes A1, A2 and A3:
VLT
®
AutomationDrive FC 300 Instruction Manual
How
to
Install
16
MG.33.A8.22 - VLT
®
is a registered Danfoss trademark.