16
5.3
Assembly procedure
5.3.1 Boiler drum installation
1.
Position the boiler body on a retaining wall.
2.
Put sealing 90 x 60 x 3 (1) onto the upper flange of the rear boiler section and screw the flange of
heating water (2) and then interconnect the other end with the heating system.
3.
Put sealing 90 x 60 x 3 (5) onto the lower flange of the rear boiler section and screw the flange of
heating water with a sleeve (6) for the fill and drain cock and then interconnect the other end with the
heating system.
4.
After connecting the boiler to the heating system screw a knee with the fill and drain valve (9) into the
sleeve of the flange of return water.
5.
Then screw the sump of thermostat G 1/2 "into the hole in the upper part of the rear boiler section
(Fig. no. 10).
Fig. no. 10
6.
Then carry out blinding of the threaded hole Js 6/4 "in the front boiler section by using a blinding plug Js
6/4". Place the seal 60 x 48 x 2 under the blinding plug.
7.
Fit the smoke pipe onto the smoke adapter and insert it into the chimney opening.
Fig. no. 11 Boiler drum installation
1
Check valve for
the manometer
2
Boiler basin
1.
Sealing
φ
90 x 60 x 3
2.
Heating water flange
3.
Washer10,5
4.
Nut M10
5.
Sealing
φ
90 x 60 x 3
6.
Return water flange
7.
Washer 10,5
8.
Nut M10
9.
Filling and draining cock