Installation Drawings
Vertiv
Large System, 3-Phase UPS Battery System Installation Manual
30
Figure 27
Front-terminal battery cabinet shipping split
Install supplied washer
, lockwasher
and bolt to secure units together
front and rear
.
Note: Jar 28 must be
moved forward or removed
to install rear hardware. Rear
cutouts are provided if rear
access is provided.
Install supplied washer
, lockwasher
and bolt to secure units together
front and rear
.
Note: Jar 16 must be
moved forward or removed
to install rear hardware. Rear
cutouts are provided if rear
access is provided.
Install snap bushing
in corner post before
routing these wires
Install snap bushing
in corner post before
routing these wires
Install snap
bushing
in corner
post before
routing these
wires
Route two supplied wires (W17)
from Jar 15 (+) to Jar 16 (-)
Note: Install bushing first.
Route two supplied wires (W16)
from Jar 1 (-) to BCB breaker in (-)
Note: Install bushings first.
T
ywrap here to
secure wires in place
Use supplied
hardware
on bus
Use supplied hardware on bus
Remove hardware
used to secure lugs
in place and discard
Connect lugs to bus
directly above insulator
and secure with supplied
hardware on bus.
T
ypically
eight places.
Cabinet A
Cabinet B
Remove these busbars and keep
the hardware to secure busbars
between Cabinet
A
and Cabinet B
Negative (-)
Positive (+)
Busbars shown
connected between
Cabinet
A
and Cabinet B
(busbar quantity varies)
Reuse supplied hardware
Jar 16
Jar 28
A
B
T
ywrap here
to secure
wires in place
T
ywrap here to
secure wires in place
T
op V
iew
Front
Detail A
Detail B
Isometric V
iew
Summary of Contents for Liebert NXL 1100
Page 2: ...Liebert Large System 3 Phase UPS Battery System Installation Manual...
Page 69: ...Specifications Vertiv Large System 3 Phase UPS Battery System Installation Manual 62 NOTES...
Page 70: ...Specifications Vertiv Large System 3 Phase UPS Battery System Installation Manual 63...
Page 71: ...Specifications Vertiv Large System 3 Phase UPS Battery System Installation Manual 64...