14
On this compute node connect Slot 4, Port 2 to controller A, Port 1 on the
Primary shelf.
15
Use the following procedure to connect Expansion Storage Shelves to the
Primary shelf.
See
“To connect Expansion Storage Shelves to a Primary shelf”
on page 59.
If you do not have any Expansion shelves at this time, proceed to the following
section to connect power cords to the hardware.
See
“Connecting the power cords to the hardware”
on page 66.
To connect Expansion Storage Shelves to a Primary shelf
1
Do the following if you have one Expansion shelf.
■
Connect one end of two SAS3 cables to the SAS3 port on the left hand
side of each RAID controller in the Primary shelf.
The blue tab on the cable must face down in the SAS3 port.
59
Hardware installation procedures
Connecting the hardware to two nodes