Marquee ACON Ultra Installation/Operation Guide
2-15
NOTE:
If projectors are overlapped, they will be scheduled to operate sequentially to prevent
interference.
2.2.3.1.8
Calibration
The Calibration routines may be run only after the initial TP setup has been completed for the test point
set. After pressing the button, The
Operation Selection
dialog appears prompting the selection of the
Test Point set on which the calibration operation is to be performed. Any combination of the selections
may be selected.
NOTE:
Depending on the selection, the displayed test pattern may need to be changed during the
completion of the routines.
After the operation is selected, the Projector Selection Dialog appears prompting the selection of the
channels on which the calibration process is to be performed. Multiple projectors may be selected.
NOTE:
If projectors are overlapped, they will be scheduled to operate sequentially to prevent
interference.
NOTE:
If Convergence Calibration is being run, only three projectors will be scheduled to perform the
calibration procedure at a time.
2.2.3.1.9
Memorization
After calibration of all three test point sets has been completed, memorization may be performed.
After pressing the button, The
Projector Selection
dialog appears prompting the selection of the channels
on which the memorization process is to be performed. Multiple projectors may be selected.
NOTE:
The displayed test pattern will need to be changed during the completion of the routines.
2.2.3.1.10
Guided TP Setup
Summary of Contents for 69871-01
Page 2: ...VDCDS Doc 79024 01 Revision 2 0 2 07 30 2007 MARQUEE ACON Ultra Operation Maintenance Manual ...
Page 3: ......
Page 4: ......
Page 5: ......
Page 19: ......
Page 31: ...Marquee ACON Ultra Installation Operation Guide 2 8 AU User Controls Settings and Operation ...
Page 67: ......
Page 75: ......