Unit Startup
RT-SVX24J-EN
171
Table 49.
Trane startup checklist
Important:
This checklist is not intended as a substitution for the contractor’s installation instruction.
This checklist is intended to be a guide for the Trane technician just prior to unit 'startup'. Many of the recommended
checks and actions could expose the technician to electrical and mechanical hazards. Refer to the appropriate sections
in the this manual for appropriate procedures, component specifications and safety instructions.
Job Name
Serial #
Job Location
Model #
Sales Order #
Ship Date
Unit DL # (special units)
Date
Starting Sales Office
Technician
Important:
Except where noted, it is implied that theTrane technician is to use this checklist for inspection/verification
of prior tasks completed by the general contractor at installation. Use the line item content to also record
the associated values onto the Trane unitary packaged equipment log.
Complete
1.
Crankcase heaters working for 8 hours prior to arrival of Trane technician performing startup
2.
Correct voltage supplied to unit and electric heaters
3.
Unit exterior inspected
4.
Disconnect all power, Unit interior free from debris/obstructions etc.
5.
Open all access doors to verify all open and close fully without any binding
6.
All wiring connections tight
7.
Unit properly grounded
8.
Copper power wiring meets sizing requirement
9.
All field control wiring for CV, SZVAV or VAV controls completed
10. All automation and remote controls installed/wired
11.
Unit clearances adequate for service and to avoid air recirculation etc.
12. All unit drain lines and traps proper
13. All coil fins inspected and straightened
14. Shipping hardware for compressors removed
15. Hold down bolts and channels from fan sections removed
16. Fan section spring isolators checked/adjusted
17.
Damper linkages tight/adjusted
18. Rail connector splice brackets installed on low side base rail
Where applicable: Evaporative condenser
19. Verify incoming water pressure is between 35-60psig, dynamic pressure (measured with valve open) for min flow rate of 30 GPM
20. Verify fan shipping brackets between fans and mist eliminators above spray distribution system have been removed
21. Verify water treatment system has been installed and approved - discontinue start-up if proof of active water treatment does not exist
Continued on next page
22. Verify conductivity controller calibration has been documented
23. Verify conductivity controller min and max setpoints have been setup
24. Verify all water and drain connections are complete
25. Verify the sump fills to within 1" of the overflow
26. Verify drain valve is set to "drain during power loss" or "hold during power loss" per job specification
Where applicable: Electric Heat
27.
Electric heat circuits have continuity
Where applicable: Gas Heat
28. Gas heat piping includes drip leg previously installed by controlling contractor
29. Gas heat flue assembly fully installed