CenTraVac™ Installation Completion Check Sheet and
Request for Trane Service
Im port ant :
A copy of this com pleted form m ust be subm itted to the Trane service office that w ill be responsible for the
start-up of the chiller. Start-up w ill NOT proceed unless applicable item s listed in this form have been
satisfactorily com pleted.
To: __________________________________________________
Trane Service Office: ____________________________________
S.O. Num ber: ________________________________________
Serial Num bers: ________________________________________
Job/Project Nam e: ______________________________________________________________________________________________
Address: _______________________________________________________________________________________________________
The follow ing item s are being installed and w ill be com pleted by: __________________________________________________
Im port ant :
Start-up m ust be perform ed by Trane or an agent of Trane specifically authorized to perform start-up and
warranty of Trane
®
products. Contractor shall provide Trane (or an agent of Trane specifically authorized
to perform start-up) w ith notice of the scheduled start-up at least tw o w eeks prior to the scheduled start-up.
Equipm ent not st art ed by Trane is not w arrant ed by Trane.
Check box if the task is com plete or if the answ er is “ yes.”
1. CenTraVac
In place and piped.
N ot e: Do not insulate the CenTraVac chiller or adjacent piping prior to the chiller com m issioning by Trane service
personnel. The contractor is responsible for any foreign m aterial left in the unit.
2 . Piping
Chilled water piping connected to:
Condenser and heat recovery condenser (as applicable)
piping connected to:
CenTraVac
Air handling units
CenTraVac
Pum ps
Pum ps
Cooling tow er
Heating loop (as applicable)
M ake-up water connected to cooling tow er
Pum ps run, air bled from system
Water supply connected to filling system
Strainers cleaned
System s filled
Rupture disk or RuptureGuard™ ventilation piping
installed
3 . Flow balancing valves inst alled
Leaving chilled water
Leaving condenser water
Optional heat recovery or auxiliary condenser water
4 . Gauges, t herm om et ers, and air vent s
Installed on both sides of evaporator
Installed on both sides of condenser and heat
recovery condenser (as applicable)
5 . Wiring
Com pressor m otor starter has been furnished by Trane, or has been configured and installed in com pliance w ith
the appropriate Trane Starter by Others specification (available from your local Trane Sales Office)
Full pow er available
Chilled water pum p (connected and tested)
Interconnecting w iring, starter to panel (as required)
Condenser water pum p (connected and tested)
External interlocks (flow sw itch, pum ps auxiliary, etc.)
Cooling tow er fan rotation checked
Chiller m otor connection (rem ote starters)
Heat recovery condenser water pum p (as applicable)
N ot e: Do not m ake final rem ote starter-to-
com pressor m otor connections until
requested to do so by the Trane service
representative!
115 Vac pow er available for service tools
All controls installed and connected
All m agnetic starters installed and connected