Table 3. Initial startup readiness checklist (continued)
☐
☐
Startup Readiness Dimension
☐
Check the box if all condenser chilled water line filters and strainers are clean.
☐
Check the box if condenser chilled water lines have been leak tested according to pre-startup instructions.
☐
Check the box if condenser reservoir (if included) is at operating level with correct water/glycol mixture.
☐
Check the box if all source/sink chilled water line filters and strainers are clean.
☐
Check the box if source/sink chilled water lines have been leak tested according to pre-startup instructions
☐
Check the box if source/sink reservoir (if included) is at operating level with correct water/glycol mixture.
☐
Check the box if high voltage wiring is installed, tested, and functional.
☐
Check the box if all water, refrigeration, electrical, and control connections between chiller/heater modules are completed.
☐
Check the box if all control wiring between modular chiller/heaters is installed, tested, and functional.
☐
Check the box if control wiring is complete, including any remote interface panel or special-purpose module wiring.
☐
Check the box if all responsible installing contractors and sub-contractors have been notified to have representatives available on site to
provide technical support for the initial start-up procedure.
☐
Check the box if full load will be available for chiller/heater on the initial start-up date.
☐
Touchscreen Interface Panel: Record version and date of the software loaded into the touchscreen interface panel:
Version: ____________________________________ Date: ________________
Note:
To view the software version, from the home screen, press the software button on the System Control screen.