Coil Piping and Connections
General Recommendations
Proper installation, piping, and trapping is necessary to ensure satisfactory coil operation and to
prevent operational damage:
•
Support all piping independently of the coils.
•
Provide swing joints or flexible fittings on all connections that are adjacent to heating coils to
absorb thermal expansion and contraction strains.
•
If the coil was ordered with factory-mounted controls, install the control valves. The valves ship
separately.
Note:
The contractor is responsible for supplying the installation hardware.
•
For best results, use a short pipe nipple on the coil headers prior to making any welded flange
or welded elbow type connections.
•
Extended drain and vent connections are provided as standard on D1 and D2 coils only. If
extended drains and vents are required on other water coils, they must be field-installed or
ordered as specials from the factory.
•
Pipe coils counterflow to airflow.
NOTICE:
Connection Leaks!
Use a backup wrench when attaching piping to coils with copper headers to prevent damage to
the coil header. Do not use brass connectors because they distort easily and could cause
connection leaks.
•
When attaching the piping to the coil header, make the connection only tight enough to prevent
leaks. Maximum recommended torque is 200 foot-pounds.
NOTICE:
Over Tightening!
Do not use teflon-based products for any field connections because their high lubricity could
allow connections to be over-tightened, resulting in damage to the coil header.
•
Use pipe sealer on all thread connections.
NOTICE:
Leakage!
Properly seal all penetrations in unit casing. Failure to seal penetrations from inner panel to
outer panel could result in unconditioned air entering the unit, and water infiltrating the
insulation, resulting in equipment damage.
•
After completing the piping connections, seal around pipe from inner panel to outer panel.
Summary of Contents for AM4A0A18S11SA Series
Page 1: ......
Page 2: ......
Page 3: ......
Page 4: ......
Page 100: ...96 CLCH SVX07C EN Installation Electrical Figure 84 Typical VFD wiring schematic ...
Page 101: ...CLCH SVX07C EN 97 Installation Electrical Figure 85 Typical starter wiring schematic ...
Page 135: ...CLCH SVX07C EN 131 Notes ...
Page 146: ...10 1 2 STEP 8 Lift the Coil section up and away from the Blower section Set aside ...
Page 178: ......
Page 188: ...2 ...
Page 189: ...3 ...
Page 190: ...4 ...
Page 201: ......
Page 202: ......
Page 203: ......
Page 204: ......
Page 205: ......
Page 206: ......
Page 207: ......
Page 208: ......
Page 209: ......
Page 210: ......
Page 211: ......
Page 212: ......
Page 213: ......
Page 214: ......
Page 215: ......
Page 216: ......
Page 250: ......
Page 251: ......