Autoped Installation Manual rev 2.0 (100722)
37
IX.1 SETUP SEQUENCE FOR DOUBLE DOOR/GATE OPERATION
IMPORTANT NOTE: The AutoPed must be initially programed for basic functions before it can be setup for Double
Door/Gate Operation. Refer to Section XI: Quick Start Programming for this purpose.
The AutoPed is capable of being linked to another AutoPed unit and working in tandem with that other unit. The two operators must
be physically connected with a CAN-Bus at terminal X117 to function as double doors; Fig IX.1
STEP 1
Move the joystick up or down to scroll through the
menu selections until you get to Double Door.
•
Press the joystick in to select the Double Door
section and you will get DoubleD on the
screen.
•
Toggle the joystick left or right to select if the
operator will be designated as one of the
following: Master A, Master B, Slave A, Slave
B.
•
An activation of the slave door will open both,
while and activation of the master will only
open the master.
•
Wire all activation devices to the slave
operator so that both units will activate from a
single input device.
STEP 2
Wire between Master and Slave/Secondary
Operators
•
Wire the AutoPed Master A to Slave A. Run
the wire between terminal X117 on each
control board. (See Fig XIV.2g, p.76 Wiring
Warning: The default setting of the AutoPed is "Low Energy." The AutoPed is ONLY approved and warranted
for Low Energy, ANSI 156.19 applications. It is the responsibility of the installing party to adhere to ANSI
156.19 standards when completing the AutoPed installation.
Use of the AutoPed for Full Energy applications is PROHIBITED. TORXUN IS NOT RESPONSIBLE FOR
LIABILITY ASSOCIATED WITH FULL ENERGY APPLICATIONS.
Fig IX.1 Double Door In Tandem
Summary of Contents for AUTOPED M10S.0028
Page 1: ...Autoped Installation Manual rev 2 0 100722 1 AUTOPEDTM OPERATOR INSTALLATION MANUAL 2022...
Page 40: ...Autoped Installation Manual rev 2 0 100722 40 SECTION X SETTING UP ELECTRIC LOCKS AND STRIKES...
Page 50: ...Autoped Installation Manual rev 2 0 100722 50 SECTION XII MENUS AND PROGRAMMING...
Page 59: ...Autoped Installation Manual rev 2 0 100722 59 SECTION XIII TROUBLE SHOOTING AND ERROR CHARTS...
Page 69: ...Autoped Installation Manual rev 2 0 100722 69 Fig XIV 2b Non Powered Activation Devices...
Page 75: ...Autoped Installation Manual rev 2 0 100722 75 Fig XIV 2f Secured Activation Devices...
Page 76: ...Autoped Installation Manual rev 2 0 100722 76 Fig XIV 2g Wiring for Double Door Gate System...
Page 77: ...Autoped Installation Manual rev 2 0 100722 77 SECTION XV SERVICE PARTS...
Page 78: ...Autoped Installation Manual rev 2 0 100722 78 XV 1 SERVICE PARTS COMPONENTS VISUAL GUIDE...
Page 80: ...Autoped Installation Manual rev 2 0 100722 80 SECTION XVI PRODUCT WARRANTY AND REGISTRATION...