2
Changing the Column
Replacing the Factory Installed Column
8
ISQ User Guide
Thermo Scientific
.
6. Open the front door of the instrument.
7. Look behind the right side of the vacuum interlock shield and twist the vent valve knob
one and a half times in a counter-clockwise direction to open the vent.
8. Wait five minutes for venting to complete.
9. Turn off the carrier gas and if used, the detector gas. See the GC documentation for
information about using detector gases.
10. Unscrew the transfer line nuts and remove the column.
11. Attach a blanking ferrule and nut to seal the end of the transfer line to prevent
contaminants from entering the MS during column conditioning.
Figure 3.
Powering Off the ISQ Instrument
Power Switch
Vacuum Interlock Shield
Vent Valve
Knob
Hydrogen Safety Screws
Hydrogen Safety Screw
(On Front Door Panel)
CAUTION - INSTRUMENT DAMAGE
Do not proceed until the instrument is vented, or
pieces of the column or ferrule might blow into the instrument. To confirm that the
instrument is vented, check how much the glass cover compresses the top cover o-ring in
the manifold. Once the o-ring surface touching the glass is about 1 mm, it is safe to open
the instrument and remove the column.
WARNING BURN HAZARD:
The injector, oven, and transfer line may be hot.
Allow them to cool to room temperature before touching them.
Summary of Contents for ISQ
Page 1: ...ISQ User Guide 1R120555 0003 Revision D January 2013 ...
Page 22: ......
Page 54: ......
Page 82: ...4 Creating a Method Creating a Method for the GC 60 ISQ User Guide Thermo Scientific ...
Page 124: ......
Page 148: ......
Page 152: ......