3 - 36
Z-45/25 Bi-Energy • Z-45/25J Bi-Energy
Part No. 237062
September 2015
Section 3 • Scheduled Maintenance Procedures
CHECKLIST
D
PROCEDURES
D-5
Calibrate the Platform Overload
System (if equipped)
Note: Genie specifications require that this
procedure be performed every 1000 hours or
annually, whichever comes first.
Yearly calibration of the platform overload system
is essential to safe machine operation. Continued
use of an improperly calibrated platform overload
system could result in the system failing to sense
an overloaded platform. The stability of the
machine is compromised and it could tip over.
Note: Perform this procedure with the machine on a
firm, level surface.
1 Level the platform.
2 Determine the maximum platform capacity.
Refer to the machine serial plate.
3 Using a suitable lifting device, place an
appropriate test weight equal to that of the
maximum platform capacity at the center of the
platform floor.
Determine the limit switch trigger point:
4 Gently move the platform up and down by hand,
so it bounces approximately 1 to 2 inches /
2.5 to 5 cm. Allow the platform to settle.
Result:
The overload indicator light and the
alarm is on.
Slowly tighten the load spring
adjustment nut by turning it clockwise just until
the overload indicator light and alarm turns off.
Note: The platform will need to be moved up and
down and allowed to settle in between adjustments.
Note: There may be an approximate 2 second delay
before the overload indicator light turns on and the
alarm sounds.
Result:
The overload indicator light and
alarm is off.
Slowly loosen the load spring
adjustment nut by turning it counterclockwise
just until the overload indicator light and alarm
turn on.
Note: There may be an approximate 2 second delay
before the overload indicator light turns on and the
alarm sounds.
Note: The platform will need to be moved up and
down and allowed to settle in between adjustments.
Summary of Contents for Genie Z-45/25 Bi-Energy
Page 1: ......
Page 203: ...6 79 Section 6 Schematics September2015 Engine Panel Wiring Diagram 6 80 ...
Page 206: ...6 82 September2015 Section 6 Schematics Power Panel Wiring Diagram 6 81 ...
Page 207: ...6 83 Section 6 Schematics September2015 6 84 CTE Option Wiring Diagram CE ...
Page 210: ...6 86 September2015 Section 6 Schematics 6 85 Charger Interlock Option ...
Page 212: ...6 88 September2015 Section 6 Schematics Hydraulic Schematic 6 87 ...
Page 213: ......