Section 3 • Scheduled Maintenance Procedures
3 - 10
GS-30 • GS-32 • GS-46
Part No. 96316
June 2009
REV F
CHECKLIST
B
PROCEDURES
11 Check the battery acid level. If needed,
replenish with distilled water to
1
/
8
inch / 3 mm
below the bottom of the battery fill tube. Do not
overfill.
12 Install the vent caps and neutralize any
electrolyte that may have spilled.
-
+
-
+
-
+
-
+
275A Fuse
F6
-
+
QD1
a
b
c
Battery Charger
U9
RD
BK
d
a
batteries B5
b
275A fuse F6
c
quick disconnect QD1
d
battery charger U9
All models:
13 Check each battery pack and verify that the
batteries are wired correctly.
14 Inspect the battery charger plug and pigtail for
damage or excessive insulation wear. Replace
as required.
15 Connect the battery charger to a properly
grounded 115V/60Hz or 230V/60Hz single
phase AC power supply.
Result: The charger should operate and begin
charging the batteries.
If, simultaneously, the charger alarm sounds
and the LEDs blink
one time
, correct the
charger connections at the fuse and battery.
The charger will then operate correctly and
begin charging the batteries.
If, simultaneously, the charger alarm sounds
and the LEDs blink
two times
, the input voltage
is too low or too high. Correct the voltage issue.
The charger will then operate correctly and
begin charging the batteries.
If, simultaneously, the charger alarm sounds
and the LEDs blink
three times
, the charger is
overheated. Allow the charger to cool. The
charger will then operate correctly and begin
charging the batteries.
Note: For best results, use an extension of
adequate size with a length no longer than
50 feet / 15 m.
Note: If you have any further questions regarding
the battery charger operation, please contact the
Genie Industries Scissor Service Department.