Section 3 • Scheduled Maintenance Procedures
Part No. 96316
GS-30 • GS-32 • GS-46
3 - 7
October 2008
REV C
CHECKLIST
A
PROCEDURES
A-2
Perform Pre-operation Inspection
Completing a Pre-operation Inspection is essential
to safe machine operation. The Pre-operation
Inspection is a visual inspection performed by the
operator prior to each work shift. The inspection is
designed to discover if anything is apparently
wrong with a machine before the operator performs
the function tests. The Pre-operation Inspection
also serves to determine if routine maintenance
procedures are required.
Complete information to perform this procedure is
available in the appropriate operator's manual.
Refer to the Operator's Manual on your machine.
A-3
Perform Function Tests
Completing the function tests is essential to safe
machine operation. Function tests are designed to
discover any malfunctions before the machine is
put into service. A malfunctioning machine must
never be used. If malfunctions are discovered, the
machine must be tagged and removed from
service.
Complete information to perform this procedure is
available in the appropriate operator's manual.
Refer to the Operator's Manual on your machine.