Model 300E Carbon Monoxide Analyzer
Instruction Manual
CALIBRATION PROCEDURES
P/N 04288 REV: A
133
The following example sets Sequence #2 to do a Zero-Span Calibration every other
day starting at 1 am on September 4, 2001, lasting 15 minutes, without calibration.
This will start ½ hour later each iteration.
Mode and
Attribute
Value Comment
Sequence
2
Define Sequence #2
Mode
ZERO-SPAN
Select Zero and Span Mode
Timer Enable
ON
Enable the timer
Starting Date
Sept. 4, 2001
Start after Sept 4, 2001
Starting Time
01:00
First Span starts at 1:00AM
Delta Days
2
Do Sequence #2 every other day
Delta Time
00:30
Do Sequence #2 ½ hr later each day
Duration
15.0
Operate Span valve for 15 min
Calibrate
NO
Do not calibrate at end of Sequence
NOTE
The programmed STARTING_TIME must be a minimum of 5 minutes later than
the real time clock (See Section 6.3.5 for setting real time clock).
NOTE
Avoid setting two or more sequences at the same time of the day. Any new
sequence which is initiated whether from a timer, the COM ports, or the contact
closure inputs will override any sequence which is in progress.