5-20
MAINTENANCE
DAILY INSPECTION (EVERY 10 HOURS)
INSPECTING THE WATER SEPARATOR
AND THE FUEL FILTERS
• Do not smoke or permit open flames
while handling fuel or working on the
fuel system.
• Stop the engine in a well-ventilated
place and allow it to cool down before
performing maintenance.
• Clean up spilled fuel immediately.
• Before performing maintenance on top
of the work bench, clean the footing and
observe the following precautions to
prevent falling.
· Do not spill oil or grease.
· Do not leave tools scattered around.
· Watch your step when walking.
• Never jump down from the machine or
the work bench. When getting on or off
the machine or work bench, use the
steps, handrails or work bench to
support your body. Your weight should
be evenly distributed among the three
contact points (one hand and two feet
or two hands and one foot).
• Do not stand on the dozer blade and
perform maintenance work. Doing so is
dangerous because of the unsteady
foothold. Use the work bench.
Water separator
1. Turn the starter switch to the ON position.
2. Inspect the water separator warning lamp.
3. If the warning lamp is flashing, drain the
water.
Refer to “Draining the water from the
water separator” on page 5-76.
Pre-fuel filter, main fuel filter
1. Open the right side cover.
2. Check if there is water in the pre-fuel filter
(1) and the main fuel filter (2).
If water collects in the filter, the float (red
ring) (3) goes up. Be sure to drain water
before the float (3) goes up to the element
(4).
3. Loose the vent plug (5) and then the drain
plug (6) to discharge water collected
inside.
4. After drainage of water, tighten each plug
and bleed air from the fuel system.
Refer to “Bleeding air from the fuel
system” on page 6-8.
Summary of Contents for TB295W
Page 1: ......
Page 11: ...1 1 SAFETY...
Page 50: ...1 40 SAFETY SAFETY SIGNS DECALS...
Page 51: ...1 41 SAFETY SAFETY SIGNS DECALS...
Page 52: ...1 42 SAFETY SAFETY SIGNS DECALS...
Page 53: ...2 1 CONTROLS...
Page 77: ...2 25 MEMO...
Page 126: ...2 74...
Page 127: ...3 1 OPERATION...
Page 155: ...3 29 MEMO...
Page 158: ...3 32...
Page 159: ...4 1 TRANSPORT...
Page 163: ...4 5 TRANSPORT Hoisting posture HOISTING THE MACHINE...
Page 166: ...4 8...
Page 167: ...5 1 MAINTENANCE...
Page 217: ...5 51 MEMO...
Page 229: ...5 63 MEMO...
Page 235: ...5 69 MEMO...
Page 246: ...5 80...
Page 247: ...6 1 TROUBLESHOOTING...
Page 255: ...6 9 MEMO...
Page 271: ...7 1 SPECIFICATIONS...
Page 278: ...7 8 SPECIFICATIONS OPERATING RANGES OPERATING RANGES...
Page 280: ...7 10 MEMO...
Page 282: ...7 12 SPECIFICATIONS 2 Piece boom LIFTING CAPACITIES...
Page 283: ...7 13 SPECIFICATIONS 2 Piece boom LIFTING CAPACITIES...
Page 284: ...7 14 SPECIFICATIONS Mono boom LIFTING CAPACITIES...
Page 285: ...7 15 SPECIFICATIONS Mono boom LIFTING CAPACITIES...
Page 286: ...7 16...
Page 287: ...8 1 OPTIONS...
Page 303: ...8 17...