24
When handling the inverter, do not remove the cushion to avoid damage to the
housing or bottom terminals.
4.4.2 Hoisting Transport
Tools
Device
Name
Requirement
Source
Crane
Load bearing capacity ≥ 180 kg
Not included in the
scope of delivery
Lifting ring
2, M12, load bearing capacity of a single ring ≥
260 kg
Not included in the
scope of delivery
Sling
1, length ≥ 2.5 m, load bearing capacity of a sin-
gle sling ≥ 600 kg
Not included in the
scope of delivery
step 1 Release the sealing screws on the mounting ears and store them properly. Anchor two M12
thread lifting rings to the hangers of the inverter.
User Manual