5
Operation
Checks and tasks to be carried out prior to commissioning
Checks and tasks to be carried out prior to commissioning
Visual inspections
WARNING
Risk of accident due to damage or other defects on
the truck!
Damage to the truck or the attachment (variant) can
lead to unpredictable and dangerous situations.
If damage or other defects are identified on the
truck or attachment (variant) during the following
inspections, the truck must not be used until it has
been properly repaired.
– Do not remove or deactivate safety systems or
switches.
– Do not change any predefined set values.
– Do not use the truck until it has been properly
repaired.
WARNING
Risk of component damage!
A deformed or damaged battery male connector
can cause overheating and related consequential
damage.
– Check the battery male connector for damage.
– If necessary, have the battery male connector
replaced by the authorised service centre.
• Check the area under the truck for leaking
consumables.
• Attachments (variant) must be properly
mounted and function according to the
operating instructions
• All decal information must be in place and
legible. Replace damaged or missing
adhesive labels in accordance with the
overview in the chapter entitled "Labelling
points"
• Any warning units (e.g. signal horn) must be
in perfect condition and function correctly
• Check the visible areas of the hydraulic sys-
tem and hydraulic oil tank for damage and
leaks Damaged hoses must be replaced by
the authorised service centre.
• The battery must be securely locked in
place
• Check the battery male connector for dam-
age (e.g. cracks, breaks or deformation of
the housing, bent or damaged contacts). If
50
172780 EN - 06/2017
Summary of Contents for R 07-25
Page 2: ......
Page 4: ......
Page 11: ...1 Foreword ...
Page 18: ...1 Foreword Environmental considerations 8 172780 EN 06 2017 ...
Page 19: ...2 Introduction ...
Page 28: ...2 Introduction Residual risk 18 172780 EN 06 2017 ...
Page 29: ...3 Safety ...
Page 45: ...4 Overviews ...
Page 59: ...5 Operation ...
Page 163: ...6 Maintenance ...
Page 212: ...6 Maintenance Maintenance intervals 202 172780 EN 06 2017 ...
Page 217: ...7 Technical data ...
Page 244: ......
Page 245: ......
Page 246: ...STILL GmbH 172780 EN 06 2017 ...