February 17, 2010
1
922-124 (3’) TRIPLE RAIL SLIDE
EQUIPMENT MAINTENANCE
Plastic Components
!
Inspect for any sharp edges or
deformities. Minor deformities
and sharp edges can be repaired
using a utility knife. Block off
access until repairs are made.
Contact distributor for
replacement parts.
Brackets
!
Inspect all four-hole clamps and
panel clamps.
!
Ensure the setscrews are tight and
in place.
!
Ensure all Torx Screws are in
place and that the bracket is
firmly attached to post.
!
Inspect the clamps for cracks and
sharp edges. Smooth any sharp
edges and fix the finish. Replace
brackets if cracked.
Hardware
!
Inspect for loose or missing
hardware. Tighten all loose
hardware and replace all missing
hardware. Block off access to
equipment if necessary.
Welds
!
Inspect all welds for cracks. If a crack is found
block access to the playground and contact your
distributor for replacement parts immediately.
Finish
!
Inspect all metal components for coating damage. If
powder coating needs to be repaired sand surface
and mask off area. Coat with primer and once the
primer has dried paint with color matching touch up
paint. Contact distributor of color matching paint.
Contact Distributor for Thermoplastic repair kit.
Slide
!
Refer to “Plastic Components” section.
!
Inspect run-out section of the slide for
standing water. Adjust the slide by
digging up existing footing and install
it slightly lower to increase the slope
of the slide.
Replacement Parts
!
Reference the parts list on page 2 of
the instruction set for this component
to identify the part/s correctly.
!
Contact your distributor to order parts.
Footings
!
Inspect all footings to ensure
equipment is secure. You must block
access to prevent access until repair is
made.
Surfacing -
Refer to the surfacing maintenance sheet.
Summary of Contents for Quick Ship 3 Modified
Page 1: ... 012 3 4 5 2 6 7 8 9 8 6 0 5 4 72 2ABCDB EBCF GHB BIGJEB KCILCA MBNOEB MBPJIIJIP JIDGCAACGJOI ...
Page 2: ......
Page 4: ......
Page 6: ......
Page 7: ...QUICK SHIP 3 MODIFIED Installation Guide ...
Page 8: ......
Page 10: ......
Page 12: ......
Page 14: ......
Page 29: ......
Page 31: ......
Page 34: ...March 10 2014 3 912 242 SQUARE DECK 46 INSTALLATION INSTRUCTION ...
Page 41: ...March 13 2014 4 922 135 3 TRANSFER STATION INSTALLATION INSTRUCTION ...
Page 51: ...March 11 2014 4 922 120 3 CORKSCREW 3 DECK INSTALLATION INSTRUCTION ...
Page 59: ...March 10 2014 4 922 126 3 3 TRIPLE RAIL SLIDE INSTALLATION INSTRUCTION ...
Page 75: ...February 17 2010 4 912 807 SAND WATER PANEL INSTALLATION INSTRUCTION ...
Page 104: ...VALUE SERIES INSTALLATION APPENDIX 4 2 10 M C_APPENDIX V1 0410 1 INSTALLATION APPENDIX ...
Page 105: ......
Page 111: ......