12-4
The annual tests consist of all the inspection and testing procedures specified in the previous
clause and the following:
a. Visually inspect all detectors and sampling points for any condition which is likely to
adversely affect their operation, such as excessive deposition of dust or coating with paint.
b. Remove at least one detector on each alarm zone circuit and confirm the fault signal is
registered at the appropriate alarm zone facility.
c. Check the operation of 20 percent of the installed heat detectors and 50 percent of the
installed smoke detectors and sampling points in each alarm zone. The procedure for testing
shall be such that all detectors are checked not less than once every 5 years for heat
detectors, and not less than once every 2 years for smoke detectors and sampling points.
d. Detectors and sampling points that fail to operate shall be repaired or replaced and retested.
e. Check the operation of an ancillary control facilities and ensure that each controlled device
can be correctly initiated.
f.
Check operation of all manual call points.
g. Check the power supply battery supervision. Disconnect the battery and check that a
“battery depleted/missing” fault occurs.
With the battery connected, measure the voltage with a calibrated voltmeter and compare the
reading with that displayed on the LCD when the battery voltage point status is selected
under Card Status for the SPS. They should agree to within 0.5V.
h. Visually inspect control and indicating equipment components for any evidence of
deterioration.
i.
Check for any building alterations, changes in the environment, or utilisation of the
protected area which would require modifications to the system.
j.
Ensure spare glasses for manual call points are available in the control panel and a tool for
replacing such glasses.
k. Record the results of all yearly maintenance procedures in the logbooks, including details of
detectors and sampling points that do not pass the visual inspection or fail to operate
satisfactorily, and notify the owner or his agent of any faults within the installation.
l.
Check that each sprinkler monitor point i.e. pumps running, main stop valve shut etc.
operate correctly.
m. Test all stair pressurization fans for automatic and manual start-stop and correct status
indicator at the Fire Indicating Panel.
Annual Tests
Procedure
Summary of Contents for 4100U-S1
Page 2: ......
Page 10: ...viii...
Page 18: ...1 8...
Page 36: ......
Page 46: ......
Page 52: ......
Page 64: ......
Page 78: ......
Page 82: ...11 4...