Command Loop Test Configuration
The periodic command delay test works for the digital transmission line only. It triggers command delay tests
at a configurable interval. The actual command transmission is not affected.
SWT3000 > Configuration > System
Connection: digital 1/2
At least one digital is selected
Address
Transmitter/Receiver < 128
SWT3000 > Configuration > Clock Synchronisation
Command periodic delay test mode
One side is master, the other side is slave
Command periodic delay test interval
Not OFF at the master side (If interval is off, no auto-
matically loop test is triggered )
3.5.16
Installation and Commissioning
3.5 Device Configuration
170
Smart Communication, SWT 3000 Teleprotection, Equipment Manual
C53000-G6040-C605-1, Edition 03.2020