7.3
Overview of start-up steps
Step
Procedure
Reference
1
Removing the transport safety devices.
see "Transport safety device", page 25
.
2
Installing the device flanges on the purge
air fixture.
see "Installing the device flange on the
purge air fixture", page 53
3
Aligning the measuring probe.
see "Aligning the measuring probe in flow
direction", page 54
5
Connecting the protective gas.
see "Connecting protective gas to the SR-
unit", page 54
6
Connecting the potential equalization.
see "Connecting the potential equalization
to the SR-unit", page 45
the potential equalization", page 44
.
7
Electrical connection of SR-unit.
see "Electrical connection of SR-unit",
page 44
.
8
GMP probe: Start-up of the purge air sup‐
ply.
see "Start-up of the purge air supply",
page 55
.
9
Installing the SR-unit on the device flange.
see "Installing the SR-unit on the device
flange", page 59
.
10
Performing the optical fine alignment of
the SR-unit.
see "Optical fine alignment of the SR-unit ",
page 60
.
11
Installing weatherproof covers (option).
see "Installing weatherproof covers
(option)", page 61
7
COMMISSIONING
52
O P E R A T I N G I N S T R U C T I O N S | GM32-Ex
8015558/YYJ8/V1.7/2016-07 | SICK
Subject to change without notice