18 |
INSTALLATION
9.
Important!
Stabilise the cooler to ensure that it is not
rocking around whilst suspended.
10. When the cooler is stable and in position carefully begin
lowering the cooler onto the transition. The dropper
transition straps should fall outside the edges of the
dropper and transition, but may need to be guided onto
the outside surface of the transition and the dropper when
the cooler is being lowered. Be extremely careful not to
damage the transition straps, communication or mains
cables during this process.
WARNING! BE EXTREMELY CAREFUL NOT TO TRAP
HANDS IN BETWEEN THE COOLER AND TRANSITION.
DO NOT USE YOUR HANDS TO GUIDE THE TRANSITION
STRAPS.
DO NOT POSITION ANY PART OF YOUR BODY
UNDERNEATH THE COOLER WHILE IT IS SUSPENDED BY
CRANE.
ILL2786-A
11. Once the cooler has been safely placed on the transition
piece, remove the crane slings and dispose of the foam
lifting blocks thoughtfully.
ILL3031-A
Securing to the dropper
12. Ensure cooler is not hung-up on the edge of the transition
anywhere. The cooler may need to be adjusted while
sitting on dropper to achieve this. Care must be taken in
maneuvering cooler not to dislodge unit or damage any
parts of cooler. Ensure the communications or mains cables
are not trapped or pinched between the dropper and tank.
Align the dropper transition straps with the pre-drilled holes
in the dropper/T-washers. Some transition straps may need
to be pulled down to meet with pilot holes in the dropper.
This can be achieved with a small screwdriver inserted into
strap holes.
13. Begin securing the cooler to the dropper using the
dropper transition fasteners provided. A total of 12x
screws are required. Only use the screws provided. If an
alternative screw is used, ensure it is the same length and
specification (as follows):
Screw TEK, Hex, Steel, 12 Gauge, 30-35mm x 14TPI,
Category 3-5 (Depending on local regulations), No seal.
Once the transition straps have been secured to the
dropper, the major cooler installation is complete.
CRANE INSTALLATION
ILL2787-A
IMPORTANT! If the pilot holes have not been drilled as per
the instruction on Page 16, abort the lift and ensure this
is completed now, before proceeding any further with the
installation.