Insert the filament
detection wires (FD1 &
FD2) into slot 5 of the #4
Panduit and route them
up the #2 Panduit on the
electrical box upright
towards the FD units.
Insert it into a Panduit slot
to keep it in place for now.
Next, run the LED light strip
wires and power switch
wires (there are 2) through
slot 6 of the #4 Panduit
and run these along the
right side Panduits and up
towards the power switch.
Also, run the upper Z limit
switch wires through the
same Panduits as well.
Insert the upper Z limit
switch, LED light strip, and
power switch wires into
the Panduit slots to hold
them in place.
gigabot
®
: unassembled
203
Summary of Contents for Gigabot
Page 1: ...Bed Frame Bed Plate Installation...
Page 26: ...F D Y Motor Z Limit Switch Installation...
Page 36: ...Wiring Y Supports Electrical Box...
Page 51: ...Wiring Preliminary Routing...
Page 64: ...Wiring Connect Components Cover Panduits...
Page 74: ...Wiring Trolley Wiring...