5. Step-by-step Guide
The following chapters will guide you step by step through preparation, installation and activation of
the RAy2 link:
•
Pre-installation check out
•
•
•
Pre-installation Checklist
Familiarise yourself with the controls and prepare your configuration ahead of the installation of the
link on the mast tube.
Both units (without antennas) can lie on a desk with flanges running parallel and facing up at an angle;
on a non-metal desk they can also face downward. In the case of units RAy2-17 and RAy2-24 turn the
unit holders so that they are roughly perpendicular to each other. In the case of units operating in licensed
bands (RAy2-10, RAy2-11), turn unit holders so that they are roughly parallel to each other. Use an
ethernet cable to connect each of the units to a PoE source and connect a PC to one of them for con-
figuration.
Take the following steps to establish a connection between the PC and RAy2 and perform a basic
setup.
Fig. 5.1: Link Configuration (RAy2-17, perpendicular holders)
RAy2 Microwave Link – © RACOM s.r.o.
36
Step-by-step Guide
Summary of Contents for Ray2
Page 2: ......
Page 6: ...6...
Page 64: ...7 3 Status Fig 7 6 Menu Status RAy2 Microwave Link RACOM s r o 64 Configuration...
Page 219: ...Appendix B Rain zone map 219 RACOM s r o RAy2 Microwave Link Rain zone map...