Scraper floor chains
• Both scraper floor chains must be tensioned simultaneously
but not strained. They should sag slightly.
Retensioning of scraper floor chains
- The tensioning screw (S) is located under the platform.
- If length of tensioning screw is no longer adequate, then
remove chain links. Always remove even numbered links (2,
4, 6,...) from both chains.
Starting transmission
Change or at least top-up
transmission oil once a year.
Topping-up
oil
- To pour in oil unscrew one of
either fastening screws (6).
- Check the oil level at the
level screw (7).
Changing oil
- Open oil outlet screw (5).
- Drain old oil and dispose of as allowed by law.
- Pour in
1,0
ltr of oil according to lubrication chart.
Cutter gears
- 0,25 l HD SAE 90
Hydraulic unit
Caution! Danger of injury or infection!
Under high pressure, escaping fluids can penetrate
the skin. Therefore seek immediate medical help!
After the first 10 operating hours and then every
consecutive 50 operating hours
- Check the hydraulic unit and lines for tightness and retighten
screw connections if necessary.
Before operation
- Check hydraulic hoses for wear.
Replace worn or damaged hydraulic hoses
immediately. The replacement hoses must meet
the manufacturer’s technical requirements.
Cleaning of machine parts
Attention!
Do not use high-pressure washers for the cleaning of
bearing- and hydraulic parts.
- Danger of rust!
- After cleaning, grease the machine according to the lubrication
chart and carry out a short test run.
- Cleaning with too high pressure may do damage to varnish.
Brake adjustment
See chapter "Brake unit"!