E2 Striking
SB Brace Frame for single-sided walls
Instructions for Assembly and Use – Standard Configuration
– Always attach transportable units
to the Brace Frame when trans-
porting.
– Always use the available
load-bearing points as well as tex-
tile straps!
– Take into account the permissible
load-bearing capacities!
– Before moving each time, always
check the mountings/wedges. If
necessary, secure wedges with
cotter pins or screws!
– Do not release the transportable
unit from the concrete with the
crane!
Procedure
1. Release element connections
between the transportable units: see
Instructions for Assembly and Use of
the formwork system.
2. Remove re-usable anchor parts.
3. Relieve load on Brace Frame SB-A0,
A, B: with rear spindle (20.7).
(Fig. E2.01)
SB-2: with Adjustment Unit (20.7).
(Fig. E2.02)
SB-1: with Quick Jack Nut (20.7).
(Fig. E2.03)
4. Attach transportable unit (element
with Brace Frame) to the crane and
move.
5. Clean transportable unit and move to
new place of operation.
Fig. E2.02
Fig. E2.03
Fig. E2.01