A2 Tie Technology
SB Brace Frame for single-sided walls
Instructions for Assembly and Use – Standard Configuration
Anchor installation with
V-Tie Holder DW 15, 20, 26
With the V-Tie Holder and Leading An-
chor Coupler, accurate assembly of the
Tension Anchor under 45° is possible.
Verification of the safe transfer of
the bearing reactions into the build-
ing and subsequently into the
ground is the responsibility of the
contractor - determining the anchor-
ing depth.
Required tools
Tension Rod
Wrench 20/26
Spanner SW 30,
36, 46, 70
Installation of the
V-Tie Holder and
Leading Anchor Cou-
pler. Concreting.
Removal of Leading
Anchor Coupler with
Spanner SW 70.
Check tie rod to en-
sure it is firmly in
place.
Untighten the hex. nut
and tie rod by means
of the spanner.
Unscrew the tie rod
and hex. nut by means
of the spanner.
Screw out tie rod with
the Tension Rod
Wrench. Fill hole.
Work sequence for re-usable tie rods
Installation of the
V-Tie Holder and
Leading Anchor Cou-
pler. Concreting.
Removal of Leading
Anchor Coupler with
Spanner SW 70.
Check tie rod to en-
sure it is firmly in
place.
Untighten the hex. nut
and tie rod by means
of the spanner.
Unscrew the tie rod
and hex. nut by means
of the spanner. Fill
hole.
Work sequence for lost tie rod
Installation in rein-
forcement
After concret-
ing
Connection to SB
Dismantling SB