C1 Connecting to the Systems
SB-2
SB Brace Frame for single-sided walls
Instructions for Assembly and Use – Standard Configuration
Panel formwork
MAXIMO, TRIO, DOMINO
Mounting the Brace Frame
1. Position the element or element unit
on timbers.
2. Place Brace Frame in position with
the crane and position on the Connec-
tor SB (34). Top edge of Brace Frame
= top edge of Connector SB.
3. Mount two Hook Straps (33) on the
lugs (Pos. 2 + Pos. 3) of the Connec-
tor SB and secure with nuts. Put
board underneath as slide protection.
(Fig.
C1.07a)
4. Release crane lifting gear.
5. Mount second Brace Frame.
6. Brace the Brace Frames with scaffold
tubes (40) (horizontal and vertical).
(Fig.
C1.07)
7. Mount concreting platforms.
8. Adjust height of the transportable unit
with the spindles.
Erection
Permissible capacity of load-bearing
point: 1.0 t with a crane sling angle
of ≤ 15°.
Erect, move, align and anchor transport-
able unit with the crane on the
load-bearing points.
Fig. C1.07