25
RCS-2 Climbing Device and Hydraulics
Assembly Instructions
C2 Commissioning
Measures taken during com-
missioning
■
Carry out any additional steps in the
assembly instructions of the manu-
facturer.
■
Never re-tighten leaky screw connec-
tions under high pressure, only after
a pressure release.
Measures
1. Check the rotary field, see Section
D4 “Climbing procedure”.
2. Check the level of the hydraulic oil
and top up, if necessary.
3. Check the temperature of the hydrau-
lic oil and bring up to operating tem-
perature, if necessary.
4. Listen out for any unusual pump
noises after starting up.
5. If you hear any unusual pump noises,
switch off and determine the cause.
6. Check the functionality of the hydrau-
lic cylinders.
7. Check components and connections
for signs of external leakage.
Electrical connection
Danger
High electric voltage at the hydraulic
unit!
Death or serious injury can result from
an electric shock.
⇒
Only qualified electricians may carry
out work and repairs on the electrical
components of the system.
⇒
Only approved, undamaged and test-
ed connecting cables should be
used.
■
Ensure that the cable length is ade-
quate.
■
Cables must be connected without
tension. Take climbing differences be-
tween uncoupled platforms of up to
0.6 m into account!
■
Observe the manufacturer’s assem-
bly instructions.
Accessories
■
Power Cable RCS MAX CEE-32A 2m,
art. no.: 135499.
■
Power Cable RCS MAX 2m, Item no.:
136532.
Summary of Contents for 135413
Page 58: ...58 RCS 2 Climbing Device and Hydraulics Assembly Instructions F2 Declaration of incorporation...
Page 59: ...59 RCS 2 Climbing Device and Hydraulics Assembly Instructions F2 Declaration of incorporation...
Page 61: ...61 RCS 2 Climbing Device and Hydraulics Assembly Instructions F2 Declaration of incorporation...