After the Gateway is wired, the next stage is to apply the ballast
material (for example, concrete blocks). To apply the ballast to the
stand, complete the following steps.
Figure 49 – Concrete Block Ballast
1. Refer to "Ballast Requirements" on page 99 in
Appendix B to determine the adequate amount of
ballast for your installation.
2. Evenly distribute the ballast material as illustrated in
3. Secure the stand and ballast material in accordance with
local code requirements.
Activating the Gateway System
After you have all the kit items in place, attached, and mounted,
you can activate the Gateway. To activate the Gateway, complete
the following steps.
Figure 50 – Activating the Battery
1. Open the door of the battery box.
2. Turn the two breakers to the
ON
position.
3. Verify that the
CHARGING LED
on the charge
controller is lit. See "Solar Power Information" on
page 77 of Appendix A.
4. Close the battery box with the locking key.
This should activate both the battery box and the
Gateway system.
R900 Gateway Installation and Maintenance Guide
41
Chapter 4: Installation of the Gateway
Summary of Contents for 13458-000
Page 2: ......
Page 3: ...R900 Gateway v4 Installation and Maintenance Guide...
Page 6: ...This page intentionally left blank...
Page 149: ......