
Installing the drop cable and LPU
Chapter 5 Installation
phn-2182_002v000
5-14
May 2011
Installing the drop cable and LPU
Perform this task to install the drop cable from the ODU to the PoE power supply, and
to provide grounding and lightning protection for the installation.
This task consists of the following procedures:
x
Preparing drop cables
on page
5-15
.
x
Assembling an RJ45 connector and gland
on page
5-16.
x
Installing and grounding the main drop cable
on page
5-18
.
x
Connecting an RJ45 and gland to a unit
on page
5-19
.
x
Disconnecting an RJ45 and gland from a unit
on page
5-21
.
x
Making a drop cable ground point
on page
5-22
.
x
Installing and grounding the drop cable at building entry
on page
5-25
.
CAUTION
The drop cable and ground cable installation must meet the requirements
defined in
Grounding and lightning protection
on page
2-11
.
CAUTION
To provide effective protection against lightning induced surges, grounding
cables must be installed without drip loops and pointing down towards the
ground.
CAUTION
To avoid damage to the installation, do not connect or disconnect the drop
cable when power is applied to the PoE power supply.
Summary of Contents for Motorola PTP 250
Page 20: ...List of Tables phn 2182_002v000 xiv May 2011 ...
Page 30: ......
Page 80: ...Data network planning Chapter 2 Planning considerations phn 2182_002v000 2 22 May 2011 ...
Page 126: ...Notifications Chapter 4 Reference information phn 2182_002v000 4 36 May 2011 ...
Page 234: ...Testing the radio link Chapter 8 Troubleshooting phn 2182_002v000 8 14 May 2011 ...