Starting programs
39
Starting programs
The CPU will process the executable program after the startup.
The program can be started in the following ways:
In the Online menu of XSoft via Start
The start command depends on the position of the OMS. You can
only call up the Start/Stop commands via XSoft in the Online menu
when it is in the RUN-P position. The current status of the PLC is
indicated by the RUN/STOP LEDs.
Using the OMS on the operator module
To start the PLC, switch the OMS from STOP to RUN-P or RUN. This
will start the program.
When changing from STOP to RUN (-P) the STOP LED will go out
and the RUN LED will light up.
The display shows:
Tabelle 2: Loading and starting programs via the OMS
RUN-P
You can use XSoft functions such as Forcing while the
program is running.
RUN
Access from the PC is not possible.
“P”, if the OMS is set to RUN-P “R” if
the OMS is set to RUN
17:45:23
P
RUN
TESTPRO.PRO
>MAIN MENU
Executable
program
loaded
OMS position
LEDs
Display
STOP
RUN
SF
Current
status:
No
STOP/RUN-P
x
–
x
STOP
PROG: ???
Operation on OMS
Load program
PC
r
PLC
Yes
STOP/RUN-P
x
–
x
STOP
Test1.pro
Start program
Switch OMS:
STOP
r
RUN-P
RUN-P
r
STOP
r
RUN-P
Yes
RUN-P
–
x
x
RUN
Test1.pro
Current
status:
Yes
STOP
x
–
–
STOP
PROG2.pro
Load program
Overwrite existing program
Yes (new)
STOP
x
–
–
STOP
Test1.pro
Start program
Switch OMS:
STOP
r
RUN-P
Yes
RUN-P
–
x
–
RUN
Test1.pro
Current
status:
Yes
RUN-P
–
x
–
RUN
STAMO.pro
Load program
Overwrite existing program
Yes (new)
RUN-P
x
–
–
STOP
Test2.pro
Start program
Switch OMS:
RUN-P
r
STOP
r
RUN-P
Yes
RUN-P
–
x
–
RUN
Test2.pro
Summary of Contents for XControl XC600
Page 4: ...II...
Page 8: ...07 04 AWB2700 1428GB 4...
Page 30: ...07 04 AWB2700 1428GB 26...
Page 40: ...07 04 AWB2700 1428GB 36...
Page 74: ...07 04 AWB2700 1428GB 70...
Page 78: ...07 04 AWB2700 1428GB 74...