9.1.2
Alternate Unloading Procedure
It is possible to unload the unit using a forklift.
1.
Remove any chains or straps securing the Shale Shaker to the trailer.
2.
Using a forklift rated to handle the required load, slide the forklift tines underneath the skid.
3.
Slowly and carefully move the unit to the desired operating position and set in place.
9.2
Placing Equipment For Operation
The operating location of the Shale Shaker should comply with the operating conditions established in paragraph
8. Examine the Shale Shaker mud flow diagrams in paragraph 21.3. Discharge and effluent flows must have clear
paths leaving the unit. Bolt-on plates located at the sides and rear of the Shale Shaker can be removed to direct
effluent flow.
1.
Place the Shale Shaker in its intended position, using the lifting techniques outlined in paragraph 7.1
2.
Identify which side(s) the effluent will run off from equipment.
3.
Remove the appropriate bolt-on skid discharge plates from the side(s) of the unit to allow desired fluid flow.
a.
Plates are secured with 9 bolts.
b.
Place removed bolt-on plates and their corresponding bolts in a safe location so they are not lost.
Figure 11. Skid Discharge Cover (Arrowed)