Operating instructions wet waste treatment unit, Model AZP 80, AZ / AP 80
Datei:BA_AZP80_AZ_AP_9633432_EN_2005-10.docx
9633432
18/36
W e reserv e the right to c hange ex ec ution and constr uction!
MEIKO Maschinenbau GmbH & Co. KG, Englerstr. 3, D-77652 Offenburg, Tel.: +49/781/203-0, Fax: +49/781/203-1121
General Electrical Regulations must be observed when connecting the machine to the
power supply.
Attention::
The fuses on site must be selected to suit the local conditions and the
appliance’s nominal current in such a way that back-up protection is
guaranteed (Germany: VDE 0100).
The mains supply cables must be provided with fuses in accordance
with regulations and must have a main switch (accessible on site or
inside the appliance for operating personnel). If the neutral conductor
(N) is not grounded, a 4 phase main switch must be used. Cables
connecting to the main power supply must be oil-resistant and sheathed
and must not be lighter than an H 07 RN-F cable.
The potential equalisation connection must be carried out in accordance
with the requirements of the local electricity supply company and all
applicable local regulations (in Germany VDE 0100 Part 540 must be
observed).
For the supply connection use a 5-pole terminal strip (L1, L2, L3, N, PE).
The electrical connection data, voltage, type of current, output can be seen on the
manufacturers’ plates on the machine.
Please check the voltage.
All electrical connections must be made inside the electrical switch cabinet by means of
marked screwed cable glands as in the circuit diagram and connected to the terminals and
the fuses provided. The unit is readily installed for connection and operation. All switching
elements are arranged in an easily accessible and clearly visible position and wired in a
splashing water protected switch box of chromium nickel steel at the front part of the unit.
All motors and valves pertaining to the unit are protected against short circuit, overload and
single phase running. The control switches and pilot lamps are easily accessible and clearly
arranged. The operation order is indicated by pilot lamps. The whole electrical installation
is made according to the local electricity supply company and all applicable local
regulations. Emergency-off switches are incorporated.
For hand-over of the unit please only ask for a specialist technician with our agency when
all connections are completed. He will check the complete unit, demonstrate its operation
and instructs the operators. Against a signature the system will be handed-over to an
authorized person.
7.6
Dosing pump
On request a dosing unit for disinfectant can be incorporated.
Observe the manufacturer’s operating instructions.