Delivery, shipping, installation and assembly
7.1
Delivery
Check that the delivery is complete immediately after receiving it by comparing it to
MEIKO’s contract confirmation and/or the delivery note..
If necessary, complain about any missing parts immediately to the shipping company and
notify MEIKO.
Check the entire installation for any damage that may have occurred during shipping.
Should you suspect any damage has occurred during shipping, you should inform:
•
the shipping company,
•
MEIKO
in writing, and also send a photo of the damaged parts to MEIKO.
7.2
Transport and installation
In order to avoid damage to the appliance or life-threatening injuries during shipping of the
installation, the following points must be observed:
•
The shipping operations may only be carried out by qualified persons who observe the
safety instructions.
In order to ensure safe shipping, the installation parts are placed on a special four-sided
wooden frame.
Incoming goods should only arrive on these wooden frames. The packing is specifically
designed to allow the appliances to be moved safely and securely using
two
pallet
trucks
.
t is possible to negotiate gentle curves if the pallet trucks are not positioned completely
under the wooden bearers.
Electric motors may project downwards from the underside of the appliance. Care must
always be taken not to damage these.
Severe damage to
motor & frame
ATTENTION!